Data center development in Northern Virginia, a brief for deal teams

Northern Virginia data center market 2026: 4,039.6 MW inventory, 0.5% vacancy, net absorption, and CBRE figures on the world's largest data center market.

MotionCRE EditorialPublished July 1, 2026 · Updated September 29, 2026

Northern Virginia is the largest data center market in the world, ending 2025 with 4,039.6 MW of inventory, a 0.5 percent vacancy rate, and 96 percent of 2026 scheduled supply already pre-committed, according to CBRE. For development teams, the binding constraint has shifted from tenant demand to powered land. Sites with high-voltage transmission adjacency, water and sewer, and achievable zoning are scarce in Loudoun and Prince William counties, which is pushing new campuses south along the I-95 corridor toward Stafford, Spotsylvania, and Richmond.

The market in numbers

Northern Virginia ended 2025 with 4,039.6 MW of data center inventory, up 37 percent year over year, according to CBRE's 2025 market recap. The market delivered more than 1 GW of new capacity during the year and still absorbed more than it built, posting 1,102 MW of net absorption, a 144 percent increase over 2024.

The supply side is effectively sold out. Vacancy sits at 0.5 percent, the lowest of any primary US market, with just 21.5 MW available, and 96 percent of the supply scheduled to deliver in 2026 is already pre-committed. CBRE notes the market holds nearly three and a half times more capacity than all secondary US data center markets combined.

MetricFigureSource and period
Inventory4,039.6 MWCBRE, end of 2025
Inventory growth+37% year over yearCBRE, 2025
Delivered in 2025More than 1 GWCBRE, 2025
Net absorption1,102 MW, +144%CBRE, full-year 2025
Vacancy0.5% (21.5 MW available)CBRE, end of 2025
Asking rates, 10+ MW$155 to $185 per kWCBRE, end of 2025
Under construction2,078.2 MW, +80%CBRE, H1 2025
2026 supply pre-committed96%CBRE, end of 2025

JLL counts the market differently, and the two firms should not be blended. Per reporting from WTOP, JLL tallied roughly 4,900 MW operating as of mid-2025, with 1,100 MW under construction and almost 5,500 MW in planning stages. Whichever baseline you use, the direction is identical: enormous installed base, functionally zero vacancy, and a forward pipeline claimed years in advance.

Northern Virginia data center net absorption and vacancy

CBRE recorded 1,102 MW of net absorption in Northern Virginia for full-year 2025, a 144 percent increase over 2024. That is the single clearest signal of how deep tenant demand runs here: the market leased more capacity than it delivered in a year when it delivered more than 1 GW. Net absorption on that scale, sustained against near-zero availability, is what keeps the market at the top of every primary-market ranking.

Vacancy finished 2025 at 0.5 percent, the lowest of any primary US data center market, with just 21.5 MW available against 4,039.6 MW of inventory. For context, 21.5 MW is roughly a single mid-size building's worth of capacity across the entire largest data center market on earth. Heading into 2026, 96 percent of the supply scheduled to deliver is already pre-committed, so the effective availability for a new tenant is close to nothing.

The construction pipeline is the only real source of new capacity. CBRE's H1 2025 trends report counted 2,078.2 MW under construction in Northern Virginia, up 80 percent year over year and the largest active pipeline of any primary US market. JLL, on its wider footprint, tracked about 1,100 MW under construction with close to 5,500 MW in planning. Because more than 90 percent of that pipeline already carries power agreements and tenant commitments through 2028, the construction pipeline is best read as a schedule of pre-sold capacity rather than a forward supply of leasable space.

What 0.5 percent vacancy means for a development team

In most asset classes, sub-1 percent vacancy would be a leasing story. Here it is a development story, because there is nothing standing to lease. With 21.5 MW available against 4,039.6 MW of inventory, tenant demand can only be satisfied by new construction, and 96 percent of 2026 deliveries are already committed.

JLL's mid-2025 read, via WTOP, is that over 90 percent of new inventory has power agreements and is committed through 2026, 2027, and into 2028. For a developer, that compresses the risk profile in an unusual way. Demand risk on a credible site is close to zero. Execution risk is the entire game: power allocation, substation timing, entitlements, water and sewer, and community opposition.

That inversion changes what a development pipeline should track. The scarce questions are upstream of design: does this parcel have high-voltage transmission adjacency, is there a utility path to energization inside the tenant's window, and will the county approve it. Sites that fail any of those tests need to die in screening, before the team sinks six figures into studies on land that will never energize.

Join CRE teams already running their deals on MotionCRE.

Pipeline value
$148.9M
14 deals3 closing soon
Deal workspaceActive
Oak Street Multifamily
Dallas, TX · Multifamily · 180 units
Value
$24.5M
Stage
Due Dil.
In stage
12d
AI Associate

The constraint is powered land, and it is moving south

The traditional core is getting harder to build in. JLL, per WTOP, tracked peak land prices up 45 percent in Loudoun County and up 38 percent in Prince William County over a single year, while public resistance and zoning challenges slow approvals in both. Development requires adjacency to high-voltage transmission plus public sewer and water, and the parcels that check every box in the core counties are largely gone or priced for perfection.

So the market is stretching down the I-95 corridor toward Fredericksburg and Richmond. The clearest recent marker is Vantage Data Centers' VA4 campus in Stafford County: a $2 billion, roughly 929,000 square foot project across three two-story buildings on 82 acres, announced in November 2025, with the first building expected in late 2027, per Construction Dive. The campus lifts Vantage's statewide capacity to 782 MW. A flagship campus landing two counties south of Data Center Alley tells you where the next five years of site work will happen.

For deal teams, the southward migration cuts both ways. Outer-corridor land is cheaper and the approval politics are friendlier, but utility timelines are less proven and every county process is a fresh entitlement fight. Teams that already run structured entitlement tracking across jurisdictions have a real advantage as the map widens.

The site funnel behind one campus

Here is the pipeline math for a developer trying to control two Northern Virginia corridor sites in 2026, each capable of supporting 100 MW or more at buildout.

Screening criteria are unforgiving: transmission adjacency, sewer and water, zoning that is by-right or plausibly achievable, and a seller willing to transact at a basis the project can carry. Assume 1 in 10 parcels survives the desktop screen, which is generous given how picked-over the corridor is, and 1 in 3 of those survives utility and entitlement diligence to reach an executed contract.

Working backward: 2 executed contracts requires roughly 6 sites in deep diligence, which requires roughly 60 parcels screened. At 6 to 8 hours of desktop work per parcel, screening alone consumes around 420 hours. Each deep-diligence site then carries 100 or more hours across utility coordination, environmental and geotech scoping, county pre-application meetings, and LOI negotiation, another 600 hours. Call it 1,000 team hours before the second contract signs, spread across 6 or more live pursuits running at once, each with its own consultants, hearing dates, and contract milestones.

That is a concurrent-deal operations problem, and it is exactly the shape of problem a pipeline board with stages like desktop screen, utility diligence, LOI, contract, and entitlement is built to hold. The teams that lose sites in this market usually lose them to their own tracking, a missed feasibility deadline or a county submission that sat in someone's inbox.

Where the market goes from here

Nationally, JLL's year-end 2025 report tracks 39 GW of active capacity across North America at a record-low 1 percent vacancy for the second consecutive year, with rents up 9 percent in 2025 and 35 GW under construction, most of it pre-committed by investment-grade tenants for 2027 and 2028 delivery. JLL also projects Texas, with 6.5 GW under construction, is positioned to overtake Virginia as the world's largest data center market by 2030.

That is a challenge to Virginia's growth rate, not its depth. CBRE's H1 2025 trends report had Northern Virginia leading primary markets across nearly every metric, with 2,078.2 MW under construction, up 80 percent. CBRE attributes the market's growth primarily to cloud workloads, which are stickier and more location-bound than AI training campuses chasing cheap power. The plausible path is a Northern Virginia that keeps growing while its share of national growth shrinks, which raises the scarcity value of every remaining close-in site.

Running a data center development pipeline

A team pursuing sites in this market is realistically juggling 6 to 10 concurrent pursuits at different stages, from parcels in desktop screening to campuses deep in entitlement. Each pursuit accumulates utility correspondence, feasibility studies, county submissions, LOI drafts, and a calendar of hearing dates and contract deadlines that do not forgive slippage.

MotionCRE gives each pursuit a deal workspace that holds the files, tasks, contacts, and key dates for that site, while the pipeline board shows the whole funnel with days-in-stage visible. For a deeper look at how data center teams structure stages and fields, see our guide to deal management software for data center developers.

The Northern Virginia data is unambiguous: demand is committed years out, and the winners will be the teams that run site acquisition as a disciplined operation rather than a series of one-off land chases.

Browse more playbooks, templates, and definitions in the MotionCRE resource library.

Join CRE teams already running their deals on MotionCRE.

Pipeline value
$148.9M
14 deals3 closing soon
Deal workspaceActive
Oak Street Multifamily
Dallas, TX · Multifamily · 180 units
Value
$24.5M
Stage
Due Dil.
In stage
12d
AI Associate
FAQ

Questions about MotionCRE

Common questions about our deal management platform for commercial real estate teams.

Book a Demo →
How big is the Northern Virginia data center market?

CBRE puts Northern Virginia at 4,039.6 MW of data center inventory at the end of 2025, up 37 percent year over year, with more than 1 GW delivered during the year. JLL, using a different methodology and footprint, counts roughly 4,900 MW operating with 1,100 MW under construction and close to 5,500 MW planned. By either count it is the largest data center market in the world, with nearly three and a half times more capacity than all secondary US markets combined per CBRE.

What is the vacancy rate for Northern Virginia data centers?

CBRE reported a 0.5 percent vacancy rate at the end of 2025, the lowest of any primary US data center market, with just 21.5 MW of available supply. On top of that, 96 percent of the supply scheduled to deliver in 2026 was already pre-committed. Functionally, there is almost nothing to lease, and new capacity is spoken for before it finishes construction.

What is Northern Virginia data center net absorption in 2026?

CBRE recorded 1,102 MW of net absorption in Northern Virginia for full-year 2025, a 144 percent increase over 2024, which means the market absorbed more capacity than it delivered even after building more than 1 GW. Heading into 2026 there is almost nothing left to absorb, since vacancy sits at 0.5 percent with just 21.5 MW available and 96 percent of the supply scheduled to deliver in 2026 is already pre-committed. Practically, 2026 net absorption is capped by how fast new capacity energizes, not by tenant demand.

Why is Northern Virginia the largest data center market?

The market grew up around dense fiber infrastructure and decades of accumulated cloud capacity, and CBRE notes its growth is still driven primarily by cloud workloads rather than AI training. That installed base attracts more of the same, since hyperscalers cluster capacity near existing regions. The result is a market with nearly 3.5 times the capacity of all secondary US markets combined, per CBRE, even as land and power constraints slow new development inside the traditional core counties.

Where in Northern Virginia are data centers being built now?

Development is migrating south. JLL notes land prices rose 45 percent in Loudoun County and 38 percent in Prince William County in a year, while public resistance and zoning fights slow approvals in the traditional core. Developers are moving down the I-95 corridor toward Fredericksburg and Richmond. Vantage Data Centers' $2 billion, 929,000 square foot VA4 campus in Stafford County, announced in late 2025, is a representative example of the shift.

Will Texas overtake Virginia as the largest data center market?

JLL's year-end 2025 North America report projects Texas is positioned to overtake Virginia as the world's largest data center market by 2030, with 6.5 GW under construction in Texas alone. Northern Virginia remains the deepest and most supply-constrained market today, but the growth at the margin is happening in markets with more available power and land. For developers, that means the remaining close-in Virginia sites carry scarcity value.

How much do data center leases cost in Northern Virginia?

CBRE reported asking rates of $155 to $185 per kW for 10 MW and larger requirements in Northern Virginia at the end of 2025. Nationally, JLL found data center rents rose 9 percent in 2025, with listings above 1 MW commanding premiums up 13 percent. With 0.5 percent vacancy and 96 percent of 2026 supply pre-committed, pricing power sits firmly with landlords and developers who control delivered capacity.